Project Timeline
Where we are now & where we're going
We are excited to share that design is complete and a contractor has been selected. Construction on this multi-site project is scheduled to begin in April and go through late 2022/early 2023. See below for estimated construction timelines for each project site.


Sylvan Way SW/SW Orchard St
Storm work: Early to mid-August
Road work: May - September


SW Kenyon St/24th Ave SW
Boardwalk: June - October
Storm work: July - August
Road work: August - September


24th Ave SW Corridor
Storm work: April - July
Road work: Late May - September
In general, when work is occurring near your home, you can expect construction noise, dirt/dust, and vibrations as well as increased construction traffic and materials/equipment staged in the right-of-way. We will share more information about anticipated start date for work on this site, construction schedule, and anticipated construction impacts once we have a contractor onboard.